A whole-home renovation needs a 30 or 40 yard container, and often more than one over the life of the project. Demolition, rough-in, and finish each produce different debris at different times, so plan for a swap rather than one container sitting for a month. Separate any masonry into its own container.
Single-room projects are easy to size. A whole-home renovation is not, because it is really three projects stacked on top of each other, each generating a different kind of waste on a different schedule.
Sizing for the total is how people end up with a 40 yard container sitting idle for three weeks, or a 20 yard that filled on day two. Here is how to think about it by phase.
The three phases and what each produces
Debris arrives in bursts, not evenly.
| Phase | What comes out | Volume | Weight |
|---|---|---|---|
| Demolition | Drywall, flooring, cabinets, fixtures, framing | Very high | High |
| Rough-in | Old wiring, plumbing, duct, offcuts | Low | Low |
| Finish | Packaging, crating, trim offcuts, cardboard | High | Very low |
Demolition typically produces 60 to 70 percent of total volume in the first several days. Finish produces a surprising amount of bulk, almost all of it cardboard and packaging, spread over weeks.
Rough-in produces almost nothing. That middle stretch is where a container sits idle burning rental days, which is the core scheduling problem on a renovation.
Sizing by scope
| Scope | Container | Price |
|---|---|---|
| Two or three rooms, cosmetic | 20 yard | $470 |
| Multiple rooms, flooring throughout | 30 yard | $515 |
| Whole home, gut to studs | 40 yard, likely two | $620 each |
| Whole home plus addition or demo | 40 yard, plus heavy container | $620 plus $350 to $395 |
The 40 yard is worth noting for a renovation specifically. It is longer rather than taller than the 30 yard, which makes it considerably easier to load by hand. On a job where crews are carrying debris out by arm rather than wheeling it, that difference matters more than the extra capacity. Our sizing guide covers the dimensions across all six containers.
One container or a swap
The 14-day rental fits a single phase well and a whole renovation poorly.
For projects running four weeks or more, a swap usually beats a long rental. Take a container for demolition, have it pulled when demo finishes, then bring a second one in when finish work starts generating packaging. You skip paying for the idle rough-in stretch entirely.
Extra days run $20 each, so the arithmetic is straightforward. If the gap between phases is more than a few days, a swap is cheaper. If it is shorter, extending is simpler.
Early pickup costs nothing, which makes this flexible. Call when demo wraps and we will collect it, then schedule the next one when you need it.
If you describe the project schedule when you book rather than container by container, we can plan the sequence with you. That is easier for everyone than calling each time something fills, particularly during busy stretches when availability is tighter.
The masonry problem
Renovations frequently uncover masonry. A brick hearth, a tiled slab, an old patio coming out for an addition, a chimney being removed.
None of it belongs in the main container. Concrete runs roughly 4,000 pounds per cubic yard, so a modest amount consumes an entire weight allowance and everything past that is $65 per ton.
Order a separate concrete and dirt container at $350 or $395 with no weight limit. On a renovation this is almost always cheaper than absorbing the overage, and having two containers on site also speeds up demolition because crews have two places to throw things.
Older Jacksonville homes
Riverside, Avondale, Springfield, and the older parts of San Marco come with specific conditions worth planning for.
Plaster and lath rather than drywall. It weighs considerably more, and a whole-home gut of a plaster house produces far more tonnage than the same house in drywall.
Narrow lots and tight placement. Many historic lots have no usable driveway, which raises the right-of-way question. Our permit and placement guide covers when that applies and what to do about it.
Mature trees. The hoist needs roughly 23 feet of vertical clearance, and the oaks in these neighborhoods routinely interfere.
Pre-1978 materials. Lead paint and asbestos are both plausible in homes of this age. Asbestos cannot go in a roll-off under any circumstances and requires licensed abatement. If you are gutting a house from that era, get it assessed before demolition rather than during.
Site logistics that save money
- Deliver the day before demo starts. A crew waiting on a truck is the most expensive hour of the project.
- Place as close to the exit as clearance allows. On a whole-home job, every extra step of carrying multiplies across thousands of trips.
- Protect the driveway with plywood under the rails, especially on pavers or a newer slab.
- Break down and flatten. Cardboard and crating from the finish phase will eat a container if nobody flattens it.
- Pull the restricted items out early. Old paint, solvents, and fluorescent fixtures surface constantly on renovations. Our guide to what can and cannot go in a dumpster has the list.
- Book before 10 AM when you need something same day.
Frequently asked questions
What size dumpster do I need for a whole-home renovation?
A 40 yard container at $620, and frequently more than one across the life of the project. A multi-room renovation with flooring throughout fits a 30 yard at $515, and a two or three room cosmetic update fits a 20 yard at $470. Any masonry should go in a separate heavy container rather than the main one.
Should I get one dumpster or swap containers during a renovation?
For projects running four weeks or more, a swap usually costs less. Demolition produces 60 to 70 percent of volume in the first several days, rough-in produces almost nothing, and finish work generates bulk packaging weeks later. Swapping means you skip paying for the idle stretch. Extra days are $20 each, so if the gap between phases exceeds a few days, swapping wins.
Is a 40 yard dumpster harder to load than a 30 yard?
No, it is easier. The 40 yard is longer rather than taller, with lower walls than the 30 yard, which matters on a renovation where crews carry debris out by hand rather than wheeling it. It also holds more. The 30 yard gets its capacity from height, which makes it better suited to loading from a truck bed or a chute.
What do I do with a brick hearth or old concrete from a renovation?
Order a separate concrete and dirt container at $350 or $395, which carries no weight limit. Concrete weighs roughly 4,000 pounds per cubic yard, so putting it in the main container consumes the entire weight allowance and generates overage at $65 per ton. Two containers on site also speeds up demolition.
What should I know about renovating an older Jacksonville home?
Plaster and lath weighs considerably more than drywall, so a gut of a historic home produces more tonnage than expected. Narrow lots in Riverside, Avondale, and Springfield often lack usable driveway placement, and mature oaks interfere with the roughly 23 feet of vertical clearance the hoist needs. Homes built before 1978 should be assessed for asbestos and lead paint before demolition.
How long can I keep a dumpster during a renovation?
The standard rental is 14 days, with additional days at $20 each and no maximum. Early pickup is free, which makes swapping flexible: call when demolition wraps, we collect it, and you schedule the next container when finish work starts producing packaging. Describing your timeline at booking lets us plan the sequence with you.